The medical staff in January 2025: midwives, doctors, pharmacist and our laboratorian
January 2025: 158 babies
In January 2025, we are grateful to announce that 158babies were born. They were all healthy!
November 22, 2023: Inauguration
On Wednesday November 22, 2023 the clinic is inaugurated by the mayor of Bulga and Tulefa.
September 2023: almost finished
After building for 9 months, we almost finished the building.
We create a garden inside the clinic as a peaceful place for our patients.
August 2023: Painting outside
Tagline here
June 2023: next steps
In June 2023, some officials of the Zemen Bank visited the construction. At the right picture Kidan is discussing with Suleyman and Gebremichael.
March 2023: ongoing process
In these months a lot of work has been done
February 2023: Concrete masonry... heavy duty
January 2023: visit TTAF board
In January 2023, the TTAF board visited the site. The team (Kidan, Bemnet, Suleyman and Grebremichael) was present. As representatives of the TTAF board, Henk Vergunst and Marleen Wassink were informed about the status of the building process.
November 2022: starting preparation
In October 2022, we got the land. In November 2022 we started to prepare to measure the land and the dimensions of the building.
Tagline here
June 2022: start of the project
Requirements for optimal care
At the start of the design, we had several requirements:
1. The design must comply with Ethiopian laws and regulations.
2. There must be a nice atmosphere for the patients
3. The building must be easy to construct
4. There must be sufficient privacy for patients and especially for women and young mothers